Earned value metrics | Management homework help

 

Resource: Tree Trimming Project Analysis Paper Grading Guide

Thomas Johnson is a timber and Christmas tree farmer who attended a project management class last year during his off-season. When the subject of earned value (EV) came up in class, Thomas wondered if he was utilizing the concept properly. 

In mid-October, Thomas hires and trains crews who work to shear fields of Christmas trees for the upcoming holiday season. In this practice, each worker uses a large machete to shear the branches of the tree into a cone shape tree, which is the desire of most customers. Thomas operates his business per the following:

  • He counts the number of Christmas trees in the field, which is approximately 24,000.
  • He agrees with customer Tom Jones to a $30,000 lump sum contract for shearing all trees in the field.
  • He receives a partial payment about 5 days after starting the project. He then estimates the actual number of sheared trees to be approximately 6,000. The actual number of trees is taken as a percent of the total to be sheared, multiplied by the percent completed by total contract amount for the partial payment [(6,000/24,000 total trees = 25% of trees trimmed), (.25 * $30,000 total payment = 5 days payment of $7,500)].

Write a 1,050- to 1,400-word paper that thoroughly answers the following questions based on the case study:

  • Is Thomas over, on, or below schedule? Explain.
  • Is Thomas using earned value as he was taught in his project management course? Explain.
  • What can Thomas do to set up a schedule and cost variance?
  • What method do you suggest for Thomas to use for any changes in project scope, such as the shape of the tree that Tom wants?
  • It appears Thomas is using the traditional method of project management. How can he accelerate the completion of this project that he has contracted for using the Agile methodology?
  • Analyze Thomas’s project performance on this project, assuming the original quote given to the customer was an estimate.

Format your paper consistent with APA guidelines. 

Calculate your order
Pages (275 words)
Standard price: $0.00
Client Reviews
4.9
Sitejabber
4.6
Trustpilot
4.8
Our Guarantees
100% Confidentiality
Information about customers is confidential and never disclosed to third parties.
Original Writing
We complete all papers from scratch. You can get a plagiarism report.
Timely Delivery
No missed deadlines – 97% of assignments are completed in time.
Money Back
If you're confident that a writer didn't follow your order details, ask for a refund.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Power up Your Academic Success with the
Team of Professionals. We’ve Got Your Back.
Power up Your Study Success with Experts We’ve Got Your Back.